TransitKC

First rail installed, next election in 2014

The first segment of streetcar track was installed on Nov. 14 on the new Main Street bridge over I-670, months ahead of schedule. It was the first since a small extension of the original streetcar on Troost Avenue was completed in 1947.

Rebuilding the Main Street bridge over I-670 wasn’t originally supposed to include track installation. Temporarily fill material was planned until full track installation in 2014. That changed when the newly-hired Construction Manager team offered to coordinate installation of excess steel rail from Dallas’ Oak Cliff Streetcar project. It was a bonus that likely wouldn’t have come together had it been in the original plan.

The rail and welding team arrived by truck a few days prior. By Nov. 12, the team had started welding 40-foot segments together to create four continuous rails that would make up the two standard gauge tracks that cross the bridge. Concrete was poured around the new track on Nov. 15. The bridge will reopen to cars and pedestrians by December and will include noise abatement, public art, wider sidewalks, and more clearance for vehicles on the freeway below.

In other Phase 1 news, City Council approved the Construction Manager contract, the purchase of four streetcar vehicles, full funding of the project, and dedicated the vehicle maintenance facility to longtime transit advocate Kite Singleton. The Construction Manager also opened a project office at 1828 Walnut, new developments have been announced along the line, and private utilities began relocating away from the tracks.

waldorail

Phase 2 election

A 2014 election for Phase 2 streetcar has been proposed, and City Council heard consultant recommendations for scope. Kansas City’s streetcar system could be as large as 10 miles by 2020, triggering a major renewal of the urban core. The top scoring corridors are:

  • Main Street south to UMKC (3.45 miles, $230 million)
  • 31st/Linwood east to Prospect (1.74 miles, $105 million)
  • Independence Avenue east to Benton Boulevard (2.17 miles, $129 million)

Phase 2 costs are in 2019 dollars and generally work out to about $60 million per mile. While the Country Club Right of Way (shown above, near Waldo shops) didn’t score well, it’s relatively low cost of implementation ($35 million per mile), dedicated right of way, and strong neighborhood support could make it an obvious extension further south from UMKC; a southern terminus for that added scope hasn’t been determined, but could be as far as Waldo through the use of single-tracking. The full consultant report is available here.

Consultants recommended a new Transportation Development District levying the same taxes and assessments as the downtown TDD. The new TDD would stretch from the Missouri River south to 63rd (or whatever the southern terminus might be) and State Line east to I-435. The 1% sales tax would apply to the entire district, while the assessments would apply only to properties a reasonable distance from the actual streetcar lines.

As with the downtown TDD, one election would form the district and a second would approve the levies. Due to the larger voting pool, a traditional election would be held, which removes the unpopular application and notary requirements specified in the TDD Act. If both new elections are successful, the downtown TDD could be dissolved with a simple vote of its board as it has no financial obligations.

Phase 2 expansion north of the river is on a different timeline — first public meeting on Nov. 21 — and may take advantage of an existing citywide TDD passed with broad support in 2008.

Comments are off for this post

Comments are closed.